The regulatory landscape of Victorian building law is changing greatly this year and probably beyond.
One legislated change is the introduction in Victoria of a developer bond regime[1].
Application and purpose of developer bond scheme
The Victorian developer bond scheme[2] chiefly affects developers, defined to mean “the owner of the land on which a residential apartment building is affixed on the date of registration of the plan of subdivision for the land”.[3] A residential apartment building is defined in the Act as a class 2 building (or part of a class 2 building) with a rise in storeys of more than 3 and containing more than 2 homes.
The developer bond scheme is the new consumer protection approach for apartment projects of more than 3 storeys (in contrast to the first resort home warranty insurance scheme administered via the Building and Plumbing Commission (formerly the VBA) for homes including apartment buildings of up to 3 storeys in respect of insurable domestic building contracts).
The developer bond is a form of security against the cost of rectifying reportable defective building work in common property or private residential lots (or other parts of a residential apartment building, if any).
Commencement
While the Act and the relevant Regulations[4] came into force on 1 July 2026, the Regulations effectively provide that operation of the bond scheme is deferred till around mid-2027, because the regime applies only where a building permit for the construction of a residential apartment building issues on or after 1 July 2027[5].
The Act establishes a three-step process that developers must comply with, where non-compliances or attempts to avoid the full application of the regime may result in significant fines for contraventions.
Developer bond regime – step 1 – issue of developer bond and notification of BPC
Under the Act, a developer must arrange for the issue of a developer bond of 2% of the total build cost of the residential apartment building, typically in the form of a bank guarantee, before an occupancy permit application can be made for the building. That is, the developer bond must be funded and its requirements complied with as a pre-condition to settlements on contracts of sale of residential lots in the building.
The Act and relevant Regulations prescribe how total build cost is calculated[6] and the required notifications to the BPC in respect of the bond and its calculation. The Act imposes fines of more than $500,000 for developers failing to arrange for the issue of a developer bond as required by the Act[7]; developers making false disclosures to the BPC about the total build cost or the amount secured by the bond[8]; and any person applying for an occupancy permit for a residential apartment building without a developer bond being in place[9]. There are limited exceptions to the developer bond regime, mainly concerning public housing and build-to-rent concessions[10]. Failure to obtain a developer bond and in the correct amount may also bring other consequences.[11]
Developer bonds are to remain in place until called or until no call is necessary, as determined by steps 2 and 3.
Developer bond regime – step 2 – assessor’s preliminary report and final report
A developer must nominate a competent and independent building assessor, seek the owners corporation’s approval of the appointment, and appoint the assessor (and pay their fees)[12]. In the case of deadlock or failure to comply with these obligations, the BPC may appoint a building assessor[13].
The building assessor must:
- undertake an inspection and provide a preliminary report as to any defective building work in the residential apartment building, between 15 and 18 months after issue of the occupancy permit[14]. It is implicit that a builder should immediately rectify the defective building work; and then
- undertake an inspection of the previously reported defective building work and prepare a final report within 18 months after issue of the occupancy permit[15]. In the case of failure to comply or unavailability of the same assessor, the BPC appoints the assessor.[16] The final report must be provided to the developer, the owners corporation, the BPC and the relevant builder.
Developer bond regime – step 3 – call or release
If the defects are not rectified, the owners corporation can call on the bond for the cost of rectifying defective building work identified in the final report. The BPC determines whether to approve the whole claim for the bond amount.
A developer bond will be released in full to the developer if an assessor report reveals no defective building work and there is no bond claim (even for an assessor’s fees)[17].
Other matters
“Developer bond” under the Act encompasses an insurance bond (if approved by the BPC)[18]. Uncommenced legislative provisions indicate that so-called decennial insurance is intended to enter the market and over time become an alternative to developer bank guarantees[19].
Conclusion
The effect of the bond scheme is to put a developer on risk in respect of defective building work and to make this so for a period longer than standard builder defects liability periods. The period of developer obligation and exposure will be from before the issue of the occupancy permit[20] till around 2 years after the occupancy permit issues[21].
The operational deferral of required developer bonds provides developers and their funders:
- time to make sure they have fully factored in the new requirements to their project work ups, funding proposals and evaluations; and
- an opportunity to modify and negotiate construction contracts with a view to backing down a longer builder defects liability period in support.
The author thanks colleague Denise Wightman for her comments & contribution.
[1] The developer bond scheme is additional to the new requirement for developers to give early notice of intention to apply for an occupancy permit that commenced on 1 July 2026, and the additional building permit levy for non-regional buildings with a build cost of over $1.5m that also commenced on 1 July 2026.
[2] In the Building Act 1993 (Vic) (as amended by the Building Legislation Amendment (Buyer Protections) Act 2025 and by the Consumer Legislation Amendment Act 2026) (the Act)
[3] Part 9B of the Act, section 137ZM
[4] Building (Developer Bonds) Regulations 2026 (Vic)
[5] Regulation 8(d). Technically, the deferral affects only step 1 – the developer bond. But due to step 2 and 3 being related to the release of (or call upon) the developer bond, the reporting steps must be effectively deferred.
[6] Section 137ZO(2) of the Act and Regulations 7 and 9. Disclosure to the BPC includes copies of the building contracts and any other documents relevant to determining the total build cost, and payment of an administrative fee of approximately $1,500.
[7] Section 137ZP
[8] Section 137ZQ(3)
[9] Section 137ZR(1) and (3)
[10] Regulation 8
[11] A newly commenced provision in the Sale of Land Act 1962 (Vic) expands a purchaser’s rights to rescind an off-the-plan contract if the developer has not correctly obtained a developer bond. Again, this must be effectively deferred in view of the deferred introduction of developer bonds.
[12] Section 137ZT to ZX and ZZ
[13] Section 137ZY
[14] Section 137ZZD
[15] Section 137ZZ
[16] Sections 137ZZE to ZZJ
[17] Section 137ZZR and Regulation 15
[18] Section 137ZN(2)(b) of the Act
[19] The Building Legislation and Treasury Legislation (Tax Relief) Amendment Act 2026, due to commence on or before 1 December 2027
[20] Section 137ZP of the Building Act 1993 Vic and other provisions
[21] Regulation 15(b) provides that even where a final report discloses defective building work, release of any remaining portion of the bond may occur 6 months after the BPC receives the final report or after the determination of any appeal or review of the BPC’s bond claim decision.
This article is for general information purposes only and does not constitute legal or professional advice. It should not be used as a substitute for legal advice relating to your particular circumstances. Please also note that the law may have changed since the date of this article.